Projet
Ribemont wind farm
Haut - de - France
After completing a series of preliminary environmental studies, Iqony established contact with representatives of the municipality of Ribemont.
In 2016, Iqony began working with the Ribemont town council to prepare a project outline for a new wind farm.
Iqony performed a series of studies and analyses to check that constructing the Ribemont wind farm was feasible. The following points were examined between 2017 and 2020:
- Wind potential
- Flora and fauna
- Geological conditions
- Landscape
- Acoustics
- And more
The Ribemont wind farm is currently planned to be built with six wind turbines, designed to supply power to 15,000 French households.
Region | Haut - de - France |
Department | Aisne (02) |
Start of project | 2016 |